Our work

Real panels. Real wiring. Real commissioning.

A look at completed project work, documented on site, not staged photography.

Lift Station Control Panel Retrofit

This project involved a full rebuild of the electrical and controls systems for a pump/lift station, covering everything from the medium-voltage switchgear room down to the last labeled terminal inside the control panel.

Full interior view of an industrial control cabinet with organized terminal blocks, relay racks, and a pump controller mounted on the adjacent panel door.
Full panel rebuild and re-termination
PLC rack integration and I/O verification
Point-to-point commissioning against as-built drawings
Open control panel showing red-jacketed control wiring terminated to labeled relay blocks beneath a WETWELL LVL BACKUP terminal strip. 1
01/05

Panel rebuild and re-termination

The existing control panel was stripped down and rebuilt with organized terminal blocks, Weidmüller relay racks, and DIN-rail mounted power supplies. Every wire was re-run, labeled, and dressed for long-term maintainability, replacing tangled, undocumented wiring with a panel that the next technician can actually read.

Technician in a hard hat reviewing a wiring schematic on a clipboard in front of an open industrial control panel with PLC racks. 2
02/05

PLC rack integration

Allen-Bradley rack-based controllers were integrated into dedicated RACK 1 and RACK 2 enclosures, with I/O wiring organized and labeled to match the control narrative for the wetwell pump and level-monitoring systems.

Control panel section labeled PUMP MONITORS and WETWELL PUMP CTL, with organized terminal blocks and a Fluke multimeter hanging on the open door. 3
03/05

Wetwell pump monitoring and backup logic

Dedicated sections of the panel were built out for wetwell level monitoring, pump control, and backup logic, labeled WETWELL LVL BACKUP, PUMP MONITORS, and WETWELL PUMP CTL, so operators and future technicians can immediately identify each circuit's function.

Row of medium-voltage GE/Emerson Evolution Series E9000 switchgear cabinets inside an electrical equipment room. 4
04/05

Medium-voltage switchgear

The project also touched the facility's medium-voltage switchgear and drive room, home to GE/Emerson Evolution Series E9000 gear. That work demands strict adherence to safety procedure and code.

Close-up of a Weidmüller DIN-rail relay rack with labeled interposing relays and a DC power supply, wired point-to-point. 5
05/05

Point-to-point commissioning

Every circuit was verified point-to-point against the as-built and red-lined schematics using a Fluke multimeter, with each verified point checked off by hand before the panel was signed off as complete.